Yavne Neot Shamir

The project in numbers

Scope of work 

  • Neot Shamir, Yavne (Complexes C + B).

  • Construction of a new residential neighborhood as an expansion neighborhood for Yavne Ha’Yeruka.

  • 2500 housing units.

Budget 

35,500,000 €

Timeline 

Notice to proceed: Q1 2019

Project Schedule: 24 Months.

Project Completed: Q4 2020

Client 

Construction Ministry.jpg
Construction Site

The Challenge

  • Working in parallel with a development contractor.

  • Construction of electrical rooms.

  • Construction of special public areas.

  • Integration and coordination with telecommunications, electricity infrastructure and municipal contractors.

The Solution

Expert project planning and good working relationships with all the involved entities in the project to ensure a smooth, safe and cost effective and timely project execution.