The project in numbers

Scope of work 

  • The valley Line is a 60 km Single Track railway from Haifa to Beit Shean.

  • Construction of superstructure, Installation and integration of modern signalling and communication systems.

Budget 

126,000,000 €

Timeline 

Notice to proceed: 2013

Project completed: 2016

Client 

Railway Tracks

Etgar engineering was selected to manage the project, consisting of reviving the historic valley railway, bringing the line back to life for a new generation of passengers. This 60 Km railway from Haifa to Beit Shean include installation and integration of modern signalling and communication systems.