Rosh Ha'ayin Compound E,
Main Road & Aqueduct Bridge
The project in numbers
Scope of work
-
Compound E consists of development work and infrastructure. Phase one in Compound E and development work for construction by developers.
-
Main access road with 2 lanes in each direction including a bridge of 100 m in length.
-
Rosh Haayin east interchange connecting to road 10 and road 5 east, a 1.2 km arterial road section includes water, drainage, lighting and preparations for urban communications and irrigation sleeves.
Budget
31,500,000 €
Timeline
Construction Schedule: 24 Months.
Project completed: Q4 2020.
Client


We are proud to have played a significant role in the Rosh Ha'Ayin East interchange project, connecting Road 10 to Highway 5 with a 1.2 km arterial road section, including water, drainage, lighting and preparations for urban communications, and irrigation sleeves, all completed to the highest standard.
The Challenge
-
Working in parallel with a development contractor.
-
On site casting of bridge sections.
-
Construction of special public areas.
-
Integration and coordination with telecommunications, electricity and municipal contractors.
The Solution
Expert project planning and management as well as good working relationships with all the involved entities in the project to ensure a smooth, safe and cost effective and timely project execution.