Road 5 
HOV/Public Transport Lanes

Project Scope

Design and construction of 2 HOV/Public Transport Lanes along the 5.5 Km route from Kesem interchange to Shaar Shomron.

General Data

Notice to proceed: April 2024

Scheduled completion: 03.2027

Project Manager: Etgar Engineering and consultancy Ltd.

Contractor: Movilei Hamercaz Cochav

Project budget: Approx. 210 million NIS

Client 

Long Exposure

Israel Roads has selected Etgar engineering & consultancy to manage the design and construction of the addition of HOV/Public Transport Lanes to road 5 from Kesem interchange to Shaar Shomron, the project will connect at the western end to the Park & go compound at Kesem interchange and create a continuous HOV/Public Transport Lanes all the way to Glilot interchange.