Project Scope

  • Addition of 13 stabling rails in addition to the existing 23.

  • Construction of housing structure to cover the added Stabling rails.

  • Relocation and clearing of existing infrastructures.

  • Construction of building to house new labs and maintenance garage.

  • Construction of 3rd track on Haturim St. 

  • Development of Nordau St. Junction.

  • Development of Shragai St. Junction.

General Data

Notice to proceed: Q2 2021

Project completed: Q1 2025

Contract Manager: Etgar Engineering and consultancy Ltd.

Project Manager: Etgar Engineering and consultancy Ltd.

Project budget: Approx. 250,000,000 €

Client 

Jerusalem Plan Team.jpg
red line night.png

The Red Line light train is a part of the Jerusalem transport authority's plan to improve accessibility via light train to a large part of the population in jerusalem, allowing for a faster commute in the city of Jerusalem. The upgrade includes a significant upgrade to the french hill depot as well as the addition of a third track on Haturim St. and development of Nordau and Shragai intersections. 