Road 65
Hadera to Afula

Project Scope

  • 48.9 Km total length of roads.

  • Construction of a new interchange of Road 4 and 65, Road 65 will pass over Road 4 to create a continuous road to Cisaria interchange.​

  • Expansion of Road 65 to include HOV lane throughout the length of the road.

  • Construction of 13 interchanges and separators along Road 65.

  • Construction of Several HOV stations along the Road.

  • Construction of lighting, sewage, drainage and electronic infrastructures.

  • Extensive landscape development and preservation along Road 65.

General Data

Notice to proceed: Availability promotion work has begun at the Nahal Hadera Interchange - Q1 2025

Expected completion: TBD

Project Manager: Etgar Engineering and consultancy Ltd.

Contractors: TBD

Project budget: Approx. 2.2 Billion €

Client 

הדמייה ואדי ערה.jpg

Road 65 is part of the national outline plan, and is intended to lead to a significant transportation improvement by massive upgrade of the road system, creation of several interchanges and establishment of public transport routes and HOV lanes. A first project of its kind in the State of Israel - giving significant preference to public transport and high-occupancy vehicles on a long intercity route. The project is divided into 6 sub sections due to the large scope of the project.