Ofakim Highway 2411

The project in numbers

Scope of work 

  • 4.7 km highway

  • 2.5 km urban roads

  • 4 bridges

  • 7 wildlife underpasses

  • 1 new intersection

Budget 

Over 75,000,000 €

Timeline 

Construction timeline: 30 Months.

Completed: Q2 2023

Client 

Desert Road

Construction of a new access road to the city of Ofakim, creating transportation infrastructure to service the new neighborhoods of the city.

The Challenge

Planning and Building 7.2 Km of combined Highways, Urban and intercity including several bridges, under strict eco restrictions for the preservation of wildlife and environment in a desert setting.

The Solution

Working closely with renowned experts to bring the project to compleation in a timely manner and within budget, allowing for the further development of the neighborhoods with ease.