The project in numbers
Scope of work
-
4.7 km highway
-
2.5 km urban roads
-
4 bridges
-
7 wildlife underpasses
-
1 new intersection
Budget
Over 75,000,000 €
Timeline
Construction timeline: 30 Months.
Completed: Q2 2023
Client


Construction of a new access road to the city of Ofakim, creating transportation infrastructure to service the new neighborhoods of the city.
The Challenge
Planning and Building 7.2 Km of combined Highways, Urban and intercity including several bridges, under strict eco restrictions for the preservation of wildlife and environment in a desert setting.
The Solution
Working closely with renowned experts to bring the project to compleation in a timely manner and within budget, allowing for the further development of the neighborhoods with ease.